Procurement review, round two

Hatta villa renovation: contractor offer evaluation

Updated after Retouch Decor's post-meeting revisions. Their scope has grown by three packages and their price by 142,100 AED. Victorian Art has answered on air conditioning only, at 3.3 times the comparable price.

Evaluation of the offers received for the Hatta villa renovation. This view carries the price groups sitting above our benchmark and the clarifications we need answered before award.

Where the Hatta villa renovation stands: the contractors we approached, what their offers cover, the budget picture, and the decisions we need from you next.

Evaluation of the offers received for the Hatta villa renovation, updated after your revised quotes. This view carries the price groups sitting above our benchmark and the points we need closed before award.

PreparedTuesday, 1 September 2026
Offer ARetouch Decor, revised
Offer BVictorian Art, plus AC quote 1108
DocumentsQ1363 rev01, Q1364 rev02, Q1365 rev01, Q1366, Ref 1103, Ref 1108
ContractorVictorian Art Interior Decoration
Documents under reviewRef 1103, Ref 1108
ProjectHatta villa renovation
StageTender review, pre-award
ContractorRetouch Decor
Documents under reviewQ1363 rev01, Q1364 rev02, Q1365 rev01, Q1366
CurrencyAED

What changed after the first meeting

Retouch Decor answered six of the eighteen clarifications, and answered them with scope rather than words. They removed the duplicated plumbing line, put approvals in writing, and added three packages that were previously sitting in Tohfa's own budget: air conditioning, whole-villa aluminium, and internal doors.

QuoteBeforeWasNowIsDelta
Q1363 gypsum and paintrev0162,250rev01, unchanged62,2500
Q1365 constructionrev00272,900rev01: duplicate plumbing line removed (−21,500), aluminium expanded from new-room windows to the whole villa (14,600 to 45,800), approvals note added282,600+9,700
Q1364 decorationrev01342,700rev02: play bedroom added 24,500, six internal doors 15,900, four external aluminium doors 9,000, re-dressing of the existing villa door 6,500398,600+55,900
Q1366 air conditioningnot previously offered0New quote: three Carrier 5 TR concealed ducted split inverter units, supplied, installed, tested and commissioned76,500+76,500
Retouch Decor total677,850819,950+142,100
Victorian Art Ref 1108no AC offer0AC quote dated 2 Sep 2026: three concealed ducted units, 13 TR total, with zoning, thermostats and bathroom extract. Printed at 250,000; Victorian Art have since said verbally that this is a typing error and the figure is 150,000. A corrected quotation has not yet been issued150,000+150,000
Victorian Art total815,150965,150+150,000

The headline price rose 21%, but the added scope is worth 153,700 on its own (AC 76,500, aluminium 54,800, internal doors and re-dressing 22,400). Against that, they gave back the 21,500 duplicate. Net of scope, the offer got cheaper, not dearer. That is a good-faith revision.

Cleared from the last reviewThe duplicate plumbing line is gone. The game or play room is now priced. Internal doors are now priced. Approvals responsibility is now written down (client's, which is a cost to Tohfa but at least it is no longer ambiguous). The new-room-only window line has become a whole-villa aluminium replacement.
Still not answeredMeasured quantities, programme and completion date, Hatta logistics and supervision, the validity wording, demolition disposal, joinery and hardware specification, warranty and defects period, and whether drainage is inside the plumbing line.
Confirmed verbally after the revisionneeds documentingWallpaper supply and fixing, the kids study desk and wardrobes, and the master wardrobe island are all inside the quoted lump sums. That closes the last three scope gaps against Victorian Art at no extra cost. None of it appears in the documents, and one of them is contradicted by the printed exclusion list.
VAT position confirmedsince this revisionRetouch Decor prices are exclusive of VAT, as they have been on previous jobs. All four quotes therefore carry 5% on top: 819,950 net becomes 860,948. Get it printed on the face of the reissued quotes with the TRN, so the contract and the invoices agree.

Summary

Retouch Decor is now close to a turnkey offer for the villa: structure, MEP, AC, aluminium, tiling labour, ceilings, paint, doors and all joinery in four quotes. Victorian Art has answered on one package only, air conditioning, quoted at 250,000 and since described verbally as a typing error for 150,000, which is still roughly twice Retouch Decor's price. The package-by-package differences have since been put to them and a revised quotation is expected, so their figure below is a current position rather than a final one. A second meeting with Retouch Decor is set for 5 or 6 September.

Retouch Decor, as quoted (4 quotes)860,948819,950 plus 5% VAT
Victorian Art, as advised1,013,408BOQ 815,150 plus AC 150,000, plus VAT
Retouch Decor, levelled≈ 868,000only an exhaust-fan allowance
Victorian Art, levelled≈ 1,278,600with VAT and fill-ins

Retouch Decor, revised

  • Four quotes, all dated 20 Aug 2026, totalling 819,950.
  • Now covers AC, all aluminium, internal doors, tiling labour, wall paint, bathroom joinery and the kitchen worktop.
  • Still lump sums with no quantities anywhere. Every line remains "1 LS" except doors and AC units.
  • Still 70% advance: about 574,000 net, or 603,000 with VAT, before work starts.
  • Approvals, permits and municipality fees explicitly excluded and placed on the client.
  • Excludes: light fittings, wallpaper, sanitary ware and mixers, kitchen appliances, door handles, porcelain and parquet materials.

Victorian Art, revision pending

  • Measured BOQ Ref 1103, 29 Aug 2026, 815,150, plus AC quote Ref 1108. The AC quote prints 250,000; they have since said verbally it should read 150,000. On the corrected figure, 965,150 plus 5% VAT.
  • Still no aluminium, no doors, no tiling, no wall paint, no worktop, no bathroom joinery, no powder room.
  • The AC quote is a lump sum with the quantity and rate columns left blank, and its payment term is "full payment".
  • The differences have been shared with them package by package; a revised quotation is expected.
  • Client name blank, location "UAE, Dubai" with Hatta not written.
  • Stronger where it does quote: 39 lm of wardrobes with glass doors and LED, bunk bed with slide, moisture and heat-rated ceiling boards, bulkheads.
  • 20% charge on any cancelled item, advance non-refundable.

Levelled cost

Both offers topped up to one common scope. Allowances use the other party's price where one exists, otherwise a Tohfa estimate marked with a tilde.

Retouch Decor, filled to common scope

ItemAED
Four quotes as received819,950
Wallpaper supply and fix: confirmed included0
Kids study desk and wardrobes: confirmed included0
Master wardrobe island: confirmed included0
Bathroom exhaust fans with ducting and grilles (~)7,000
Subtotal826,950
VAT 5%41,348
Levelled total≈ 868,298

Victorian Art, filled to common scope

ItemAED
BOQ subtotal as received815,150
Air conditioning, three ducted units (VA corrected figure)150,000
Floor and wall tiling labour (RD price)73,700
Whole-villa aluminium windows (RD price)45,800
Bathroom vanities, mirrors, partitions (RD price)37,300
Internal wall paint (RD price)24,500
Kitchen porcelain worktop and splashback (~)18,000
Internal doors, six (RD price)15,900
Main entrance door (RD price)15,600
External aluminium doors, four (RD price)9,000
Re-dressing existing villa door (RD price)6,500
External paint to new area (RD price)6,250
Subtotal1,217,700
VAT 5%60,885
Levelled total≈ 1,278,585

Retouch Decor is now scope-complete against Victorian Art on every package, and absorbs 153,700 AED of work that was previously a separate Tohfa procurement line. That is the real commercial news in this revision: it is not just a cheaper contractor, it is fewer contracts, fewer interfaces and less of Tohfa's own management time.

Still outside both prices: sanitary ware and mixers, light fittings, tile and parquet materials, kitchen appliances, door handles, wallpaper (RD), curtains and loose furniture, municipality approvals and fees, structural drawings for the new room, handover cleaning.

Group by group

Seventeen work packages. Retouch Decor figures are the revised ones; Victorian Art is unchanged.

Work packageRetouch DecorVictorian ArtDifferenceReading
1. Demolition and removal15,60042,000+26,400VA names twelve walls and removals with disposal. RD remains one line. Disposal and skips still unconfirmed on the RD side.
2. New room structure65,00048,000−17,000Unchanged. Different build-ups; neither prices structural drawings, and RD now states permits are the client's.
3. Aluminium windows and doors54,800Excluded−54,800New. RD now removes all existing aluminium and installs thermal-break double-glazed windows villa-wide (45,800), plus four external doors (9,000). No window schedule or count given.
4. Plumbing and waterproofing47,50054,000+6,500The 21,500 duplicate is gone, so RD now sits slightly below VA. But RD's single line says water pipes only; drainage is not named. VA names supply, drainage, floor drains, chasing and waterproofing to floors and walls.
5. Electrical first fix35,00026,500−8,500Unchanged. Neither includes accessories or fittings.
6. Air conditioning76,500150,000+73,500Both now quoted, and they still disagree by about two times. RD: three Carrier 5 TR units, 15 TR total, 5,100 per TR. VA: three Daikin or Carrier units, 13 TR total with zoning and bathroom extract, 11,538 per TR on the corrected 150,000. Their printed quote says 250,000 and has not been reissued.
7. Gypsum ceilings and paint62,250102,550+40,300RD unchanged and now carries a hidden risk: the ceiling price predates the AC package, so bulkheads for ductwork and grille openings may not be inside it. VA has no wall paint at all.
8. Tiling and parquet labour73,700Excluded−73,700Unchanged. Still the largest single gap in the VA offer.
9. Entrance37,10019,720−17,380RD includes the 15,600 main door; VA excludes all doors.
10. Majlis and dining51,60059,200+7,600Comparable intent. VA adds glass and steel-supported shelving.
11. Living room29,00058,250+29,250VA's TV unit alone is 24,200 against RD's 15,500 TV wall, and VA adds wallpaper and corner cladding.
12. Bathroom joinery37,300Not quoted−37,300Three vanities with porcelain tops, mirrors and shower partitions. VA has no bathroom furniture and no powder room.
13. Kitchen63,500111,800+48,300VA is Egger across six cabinet groups but excludes the worktop; RD is MR MDF with porcelain top and splashback included.
14. Master bedroom84,700158,520+73,820Driven by wardrobes: VA 39 lm at 2,550 with glass doors and LED plus an island (109,250) against RD's 52,500 dressing room.
15. Kids bedroom39,50082,740+43,240VA itemises bunk bed with slide, library, desk, wallpaper and 9.6 lm wardrobes. RD confirms the desk, wardrobes and wallpaper are inside their 39,500, which makes it the better-value line of the two by a wide margin. Get it written down.
16. Play or game room24,50051,870+27,370New on the RD side. RD offers cladding, desk and bench. VA offers cladding, a seating cabinet and 11.5 lm of wardrobes. Not the same room content; confirm which the drawing shows.
17. Internal doors and re-dressing22,400Excluded−22,400New. Six internal doors at 2,650 plus re-dressing the existing villa door. The door specification is a concern; see cautions.
Total before VAT819,950965,150+145,200Both exclusive of VAT. With 5% added: 860,948 against 1,013,408.

The two totals are now within 4,800 AED of each other, which is a coincidence and not a comparison. The scope behind them differs by roughly 300,000.

Item by item

Revised Retouch Decor lines paired with the closest Victorian Art equivalent. Rows shaded gold are new or changed since the first review.

ElementRetouch Decor, revisedAEDVictorian ArtAED
Enabling and civil
ApprovalsNote added: all government approvals, permits and municipality fees are the client's sole responsibility and are not in the priceexcludedGovernment clearance and passes to be arranged and paid by the ownerexcluded
DemolitionNew wall openings per plan, strip bathroom floor and wall tiles, remove outer wall layer15,600Twelve named items: walls, openings, removal and disposal of bathroom finishes, wardrobes and kitchen42,000
Additional roomConcrete, bricks, sandwich-panel ceiling with thermal insulation, plaster, paint preparation65,000Blockwork with plaster 18,500; sandwich panels with columns 22,000; lean concrete blinding with mesh 7,50048,000
Aluminium windowsRemove all existing aluminium windows and doors; supply and install new thermal-break, double-glazed windows as per site requirement. Previously 14,600 for the new room only45,800Excluded0
External aluminium doorsSingle-leaf thermal break with double glass, 4 nos at 2,2509,000Excluded0
PlumbingRedistributing water pipes for bathrooms and kitchens. Second identical line at 21,500 withdrawn32,000Supply and drainage pipes, floor drains, supply and sanitary points, chasing and making goodin 54,000
WaterproofingBathroom floor insulation15,500Waterproofing to bathroom floors and wallsin 54,000
Concealed cisternNot mentioned0Cement board enclosure to conceal WC cisternin 54,000
Electrical first fixRedistribute internal wiring, external kitchen and new room35,000Wiring, conduits, lighting, LED, downlight, track, decorative, power, AC, water heater and TV points, relocation of existing26,500
Air conditioningCarrier 5.0 TR concealed ducted split inverter, 3 units at 25,500, with FCU, condensing unit, refrigerant piping, controls, condensate drain, supply and return ductwork, insulation, grilles and diffusers, flexible connections, supports and vibration isolation, tested and commissioned. R-410A, 52°C ambient, 380 to 415 V three phase76,500Ref 1108: 3 concealed ducted, 13 TR total. Living, dining and majlis 6 TR; master and dressing 3 TR; kids, game room and hallway 4 TR. Daikin or Carrier, wall thermostats, insulated copper and drain piping, ducts with insulation, supply diffusers and return grilles, bathroom exhaust fans, gas charging and air balancing250,000
Ceilings, paint and floors
Gypsum ceilingsGalvanised steel structure with Knauf board, all villa, as per drawing31,500Standard Knauf 190 sqm at 250; MR green 30 sqm at 275; HR red kitchen 25 sqm at 300; bulkheads 30 sqm at 375; 80 light openings at 7580,500
Internal paintFenomastic, all villa24,500Two coats Jotun to ceilings only, 245 sqm at 90. No wall paint22,050
External paintDecorative paint matching existing, new area6,250Not quoted0
Floor tiling and parquetFix ceramic or parquet to all areas with skirting; materials by client42,500Excluded0
Wall porcelainFix porcelain to bathrooms and kitchen; materials by client31,200Excluded0
Doors
Main doorAluminium frame, double tinted glass, solid-core veneered leaf, hinges and closer; handle by client15,600Excluded0
Internal doorsSolid wood frame and architrave, hollow chipboard core leaf with veneer, 6 nos at 2,65015,900Excluded0
Existing villa doorReplace the old dressing to match the concept6,500Not applicable0
Reception spaces
Entrance claddingMDF laminated cladding, cabinet, clear mirror cladding21,500Marble-effect cladding, gypsum cladding, DB cabinet doors, corner cladding, LED cladding, backlit mirror or console19,720
Majlis claddingMDF laminated with porcelain36,000Marble-effect 4.5 sqm at 1,900; LED cladding 21 sqm at 1,150; two further panels≈ 48,200
Buffet or consoleMDF laminated buffet with shelves15,600Console with marble top 4,300; glass shelves 6 at 400; wooden shelves with steel supports 3 at 1,500≈ 11,000
Living claddingMDF laminated, gypsum cladding and porcelain13,500Cladding 22.5 sqm at 1,050; corner cladding 3 lm at 1,900; wallpaper 10.5 sqm at 45034,050
TV wall or unitMDF laminated TV wall with shelves and porcelain15,500Wooden TV unit with rounded edges24,200
Bathrooms and kitchen
Powder roomPorcelain-top counter, built-in sink, wood shelf, mirror10,500Not quoted0
Master bathroomCounter with porcelain top, sink, drawer and shelf, mirror, wall cabinet, glass shower partition14,500Not quoted0
Kids bathroomCounter with porcelain top, sink, drawer and shelf, mirror, shower partition12,300Not quoted0
KitchenMR MDF laminated kitchen and island, soft-close runners and hinges, porcelain top and splashback; appliances by client63,500Egger lower 26,750, upper 21,500, pantry 12,750, glass pantry 28,500, island with dining table 10,800, second pantry 11,500. Worktop excluded111,800
Bedrooms
Master claddingMDF laminated with porcelain15,50021.6 sqm at 1,05022,680
HeadboardSolid frame with upholstered fabric wall8,200Fabric headboard 6 sqm at 1,200; wallpaper 4.2 sqm; wooden frames 100 lm at 3012,090
Dressing desk or vanityMDF laminated with mirror and porcelain top8,500Wooden vanity with mirror14,500
Wardrobes or dressing roomMDF laminated dressing room, aluminium-framed doors with 6 mm tinted glass52,50039 lm at 2,550 with glass doors, LED, shelves and drawers = 99,450; island 3.5 lm at 2,800 = 9,800109,250
Kids bedroomSteel structure and MDF laminated bedroom, wall cladding, base bed with soft-close drawer39,500Bunk bed with slide 33,000; library 6,600; study desk 14,430; wallpaper 19 sqm at 450; wardrobes 9.6 lm at 2,10082,740
Play or game roomWall cladding, desk and bench in laminated MDF as per design24,500Cladding 17.4 sqm at 1,050; seating cabinet 9 lm at 1,050; wardrobes 4.5 lm and 7 lm at 2,10051,870
Totals before VAT819,950965,150

The AC packages, head to head

Both contractors have now priced air conditioning. The printed Victorian Art quote reads 250,000; they have since said verbally that this is a typing error and the figure is 150,000. Even corrected, they sit 73,500 above Retouch Decor, close to double, for two tons less cooling. Neither price has been substantiated, and until a corrected quotation is issued and a heat load produced, neither should be ordered.

PointRetouch Decor, Q1366Victorian Art, Ref 1108
Price76,500 net150,000 net as advised verbally, 157,500 with VAT. The issued quotation still prints 250,000
Units3 concealed ducted split inverter, 5.0 TR each3 concealed ducted, 6 TR, 3 TR and 4 TR
Total capacity15 TR13 TR
Price per TR5,10011,538 on the corrected figure, 19,231 as printed
BrandCarrier, namedDaikin or Carrier, "premium quality", not fixed
ZoningNot statedLiving, dining and majlis 6 TR; master and dressing 3 TR; kids bedrooms, game room and hallway 4 TR
Controls"Control system", count not givenWall thermostats, one per unit
DuctworkSupply and return ductwork, insulation, grilles and diffusers, flexible connections, supports, vibration isolationDucts with insulation, supply diffusers, return grilles
Bathroom extractNot mentionedExhaust fans with ducting and grilles
PipingRefrigerant piping and condensate drainInsulated copper gas lines and water drain pipes
CommissioningTesting and commissioningGas charging, air balancing, full system startup
Technical detailR-410A, 52°C ambient rating, 380 to 415 V three phaseNone given
Quantities on the quote3 units at 25,500Quantity and rate columns left blank; one subtotal
Payment70% advance, 30% on completion"Full payment", plus non-refundable advance and 20% cancellation fee

Victorian Art's document is the better specification. It states the zoning, names the thermostats, and includes bathroom extract, which Retouch Decor omits entirely. Retouch Decor's document is the better engineering disclosure: refrigerant type, ambient rating and power supply, none of which Victorian Art gives.

Neither price is verified, and both are outside the range you would expecthighFor a villa of this size, a three-zone concealed ducted system with full ductwork, insulation, grilles, copper, drains and commissioning would normally land somewhere between these two figures, not at either end. Retouch Decor at 5,100 per TR is low enough to suggest the ductwork scope is thinner than the wording implies, or the equipment tier is not what "Carrier" suggests. Victorian Art at 11,538 per TR now sits closer to a plausible range, which is itself the problem: a 100,000 movement described as a typing error, on a package with no quantities behind it, is not a price you can rely on until it is reissued.

What both offers still miss

What to do about it

  1. Keep the package with the main contractor and substantiate it there. Hatta is remote, and air conditioning touches ductwork, ceilings and electrical, all of which the main contractor already holds. A separate AC supplier would add a second mobilisation to Hatta and put the ceiling interface across two contracts, which costs more in coordination than a benchmark is likely to save.
  2. Ask both for the heat load calculation, room by room, with the unit allocation and thermostat count. Whoever cannot produce one has not engineered the system, they have guessed it.
  3. Level the scope before comparing again. Add bathroom extract and the new room to Retouch Decor; ask Victorian Art for refrigerant type, ambient rating, power supply and a fixed brand rather than "Daikin or Carrier".
  4. Price-check the equipment rather than the package. Ask for the equipment schedule with model numbers and capacities, then check those models against dealer pricing directly. Equipment is the one part of an AC price that can be verified without another contractor, and it tells you whether the balance is ductwork and labour or margin.
  5. Use the two offers as the cross-check. You already hold two independent AC prices for the same villa. Put each contractor's per-ton rate and cost split to them and let them justify it.

Scope gaps

Only Retouch Decor prices

  • Whole-villa aluminium windows (45,800)
  • External aluminium doors, four (9,000)
  • Internal doors, six (15,900)
  • Re-dressing the existing villa door (6,500)
  • Main entrance door (15,600)
  • Floor and wall tiling labour (73,700)
  • Three bathroom vanities with mirrors and partitions (37,300)
  • Internal wall paint (24,500)
  • External paint to the new area (6,250)
  • Kitchen porcelain worktop and splashback (inside 63,500)

Only Victorian Art prices

  • Bathroom exhaust fans with ducting and grilles
  • Room-by-room AC zoning stated on the quote
  • Game room wardrobes, 11.5 lm, against RD's cladding, desk and bench
  • Bulkhead ceilings, 80 light openings, MR and HR ceiling boards
  • Concealed WC cistern enclosures
  • Waterproofing to bathroom walls, not only floors
  • Named drainage and floor drain points
  • LED-lit cladding, backlit mirror, glass and steel shelving, DB cabinet doors
  • A stated six-month programme

Neither prices, Tohfa budget

  • Municipality approvals, permits and fees, now explicitly on the client
  • Structural drawings for the additional room
  • Sanitary ware, WCs, mixers, accessories
  • Light fittings, chandeliers, spots, switches and sockets
  • Porcelain, ceramic and parquet materials
  • Kitchen appliances
  • Door handles and ironmongery
  • Curtains, loose furniture, styling
  • Site power, water, storage, clearance
  • Handover cleaning, snagging, warranty terms

Exclusions register

Part A. Retouch Decor exclusions

Stated on the quotes

ItemWhere statedDoes Victorian Art rescue it?Action
Spot lights, chandeliers, wall lightsQ1364 rev02, ExcludeNo. VA excludes electrical accessoriesTohfa supplies. Design-led choice, keep it in-house
WallpaperQ1364 rev02, ExcludeVA prices 33.7 sqm at 450ContradictionConfirmed included verbally. Delete the line from the exclusion list in the reissue
WCs, mixers and sanitary fixturesQ1364 rev02, ExcludeNo. VA excludes the sameTohfa supplies. See Part C
Kitchen appliancesQ1364 rev02, Exclude and the kitchen line noteNo. Absent from the VA BOQTohfa supplies. Confirm cut-out sizes with the joiner early
Door handles and ironmongeryQ1364 rev02, Exclude, and the main door lineNo. VA excludes doors entirelyTohfa supplies for 11 leaves. Confirm backset and hinge type with RD
Porcelain and parquet materialsQ1365 rev01, ExcludeNo. VA excludes both supply and installationTohfa supplies materials, RD fixes for 73,700. Agree wastage percentage
Government approvals, permits and municipality feesQ1365 rev01, Authorization noteNo. VA places the same on the ownerTohfa owns it outright. See Part C
Client-provided facilitiesAll four quotes, list left blankVA specifies power, water, storage and clearanceOpenMake RD fill the blank list in before signature

Silent: no line, no exclusion, simply absent

ItemVictorian Art priceWhy it mattersAction
Bathroom exhaust fans with ducting and grillesin Ref 1108Bathrooms with no extract fail on damp regardless of how good the waterproofing isAllowed at 7,000 in the levelling. Ask RD to price it
Drainage pipeworkin 54,000The RD line says "water pipes" only. Drainage is the larger half of the jobConfirm it is inside the 32,000, in writing
Bathroom wall waterproofingin 54,000RD prices floor insulation only. Shower walls need tankingConfirm scope and product
Concealed WC cistern enclosurein 54,000Affects wall build-up and tiling setting-outAsk whether cisterns are concealed or exposed in the design
Moisture and heat resistant ceiling boards15,750VA specifies green board to bathrooms and red to kitchen. RD says "Knauf board" throughoutConfirm board grades are inside the 31,500
Ceiling bulkheads and light openings17,250RD's ceiling price predates their own AC quote. Ductwork needs bulkheadsThe highest-risk silent gap. Confirm in writing before ceilings start
Game room wardrobes, 11.5 lm24,150RD's 24,500 play room covers cladding, desk and bench onlyConfirm what the drawing shows for that room
Demolition disposal, skips and waste feesin 42,000Hatta tipping and haulage is not trivialConfirm inside the 15,600
Programme and completion date6 months statedNo date means no delay remedyContract condition
Warranty and defects liabilityAlso absentNeither contractor offers oneContract condition. See Part C

Part B. Victorian Art exclusions

Stated on the quotes

ItemWhere statedDoes Retouch Decor rescue it?Action
Porcelain and parquet, supply and installationRef 1103Yes. Fixing labour 73,700, materials by TohfaA third trade in wet areas VA waterproofs. Coordination risk sits with Tohfa
Kitchen marble, meaning the worktopRef 1103Yes. Inside the 63,500 kitchenAsk VA to price it or the kitchen is unusable as quoted
House doors and aluminium windowsRef 1103Yes. 45,800 plus 15,900 plus 15,600 plus 9,000 plus 6,50092,800 of work VA leaves to others
Sanitary fixtures and bathroom accessoriesRef 1103No. RD excludes the sameTohfa supplies. See Part C
Electrical accessories, sockets and switchesRef 1103No. RD excludes fittings tooTohfa supplies. See Part C
Any accessory not specified by the clientRef 1103 and 1108RD has no equivalent open clauseOpen-endedThis is a blank cheque. Ask them to define it or delete it
Electricity and water at siteRef 1103 and 1108RD leaves the facilities list blankTohfa provides. See Part C
Storage area and site clearanceRef 1103 and 1108RD silentTohfa provides
Government clearance and passesRef 1103 and 1108RD excludes the sameTohfa owns it

Silent: no line, no exclusion, simply absent

ItemRetouch Decor priceWhy it mattersAction
Internal wall paint24,500BOQ item 41 is two coats of Jotun to ceilings only. Not one wall is painted anywhere in the villaThe largest silent gap in the VA offer. Price it
Bathroom vanities, mirrors, shower partitions37,300Three bathrooms with MEP, ceilings and tiling but no furniturePrice all three
Powder room, in its entirety10,500The room does not appear anywhere in the BOQAsk whether it was in the drawings they priced
External paint to the new area6,250New blockwork left unpainted against an existing painted villaPrice it, matching the existing finish
Windows to the additional roomin 45,800Follows from the aluminium exclusion but is easy to missConfirm who glazes the new room
AC to the additional room and external kitchenCoveredRef 1108 zoning names living, master, kids, game room and hallway. Not the new room or the external kitchenRetouch Decor confirm both are inside their AC scope. Victorian Art must price them
Quantities on the AC quote3 units at 25,500Ref 1108 leaves the quantity and rate columns blank, which is how a 100,000 error survives to issueDemand a breakdown
Warranty and defects liabilityAlso absentNeither contractor offers oneContract condition

Part C. Missing from both, regardless of who wins

These items sit outside every quote on the table. They are Tohfa's own budget and Tohfa's own risk, and they are the reason the contractor price is not the project price. Allowances are indicative Tohfa estimates for budgeting, not quotations.

ItemWhy it falls out of bothOwnerAction neededAllowance
Statutory and professional
Municipality permit, fees and NOCs for the additional roomBoth exclude government approvals in writingTohfaDecide who submits, before the new room starts12,000
Structural drawings and engineer sign-offNeither prices design for the new roomTohfaAppoint an engineer now, it is on the critical path8,000
Testing certificates and authority inspectionsNeither mentions electrical or plumbing certificationAsk contractorMake it a handover condition4,000
Contractor all-risk and third-party insuranceAbsent from every quoteAsk contractorRequire a policy copy before mobilisation8,000
Defects liability and warrantyNeither states any periodContractual12 months on works, longer on waterproofing and AC compressor0
Materials Tohfa must supply
Porcelain, ceramic and parquet materialsRD excludes materials, VA excludes supply and installationTohfaSpecify and order early, long lead items70,000
Light fittings: spots, chandeliers, wall, track, LED stripRD excludes them, VA excludes electrical accessoriesTohfaFreeze the lighting layout before ceilings close45,000
Kitchen appliancesBoth exclude, both note client supplyTohfaGive cut-out sizes to the joiner before manufacture40,000
Sanitary ware: WCs, basins, mixers, bidet sprays, shower setsBoth exclude sanitary fixturesTohfaSelect before first fix so points land correctly35,000
Switches, sockets and DB accessoriesBoth exclude electrical accessoriesTohfaConfirm finish and gang counts with the electrician12,000
Water heater unitsBoth price the points, neither prices the unitsTohfaConfirm capacity and location per bathroom8,000
Door handles and ironmongeryRD excludes handles, VA excludes doors entirelyTohfa11 leaves. Match backset to the door spec6,000
Bathroom accessories: towel rails, hooks, holdersBoth exclude accessoriesTohfaFix positions before tiling6,000
Works neither contractor priced
Fresh air provisionNeither mentions itAsk bothConfirm whether the design requires it0
Smoke detectors and fire safetyAbsent from both electrical scopesTohfaCheck the Hatta requirement5,000
Labour mobilisation and accommodation in HattaNeither prices it separatelyAsk contractorConfirm it is inside the price, not a later claim0
Site and handover
Site electricity and waterBoth place it on the ownerTohfaArrange supply before mobilisation6,000
Storage area and site clearanceVA states it, RD leaves the list blankTohfaAllocate a secure store on site3,000
Handover cleaningNeither prices itTohfaBudget a deep clean after snagging4,000
Curtains, blinds, tracks and pelmetsOutside both scopesTohfaCoordinate pelmet details with the ceiling contractor35,000
Loose furniture, rugs, art and stylingOutside both scopesTohfaSeparate budget, separate programmeseparate
Identified allowance, excluding loose furniture and styling307,000

What this means for the project budget

Awarding Retouch Decor at the levelled 868,298 does not cost 868,298. Add the 307,000 identified above and the real figure is about 1,175,000 AED before any loose furniture. The contractor's quote is roughly 74% of the spend.

Three of these items sit on the critical path and should be started this month regardless of who wins: the municipality permit and structural drawings for the additional room, the tile and parquet selection, and the lighting layout. The first delays the build, the second delays the wet trades, and the third has to be frozen before any ceiling closes.

Where we are

We took the approved design to market, reviewed both offers line by line, and pushed each contractor to close the gaps. We are not yet ready to award.

The two offers

Both shown on the same scope, so each figure includes an allowance for what that contractor leaves out.

Retouch Decor
868,300
Victorian Art
1,278,600

Levelled, including VAT. Victorian Art is 410,300 higher, about 47%, and will move again on their revision.

Some of the gap is specification: Victorian Art carry longer wardrobe runs and a heavier ceiling build-up. Most of it is price level. Their offer also excludes seven packages the villa needs, from tiling to doors to wall paint.

By work package

A missing bar means that contractor does not price the package at all.

Retouch Decor Victorian Art
Joinery and fit-out
351,600542,100
Air conditioning
76,500150,000
Ceilings and paint
62,250102,550
Structure and new room
80,60090,000
Plumbing and electrical
82,50080,500
Doors, windows, aluminium
92,800not priced
Tiling and porcelain
73,700not priced

Before VAT. Totals 819,950 and 965,150.

Joinery drives most of the gap at 190,500. Air conditioning is 73,500 higher for two tons less cooling, and only after a 100,000 verbal correction. On structure, plumbing and electrical the two are within a few percent, so the rates are close and the difference sits in fit-out and equipment.

The budget picture

A contractor's quotation is not the project cost. We buy some items directly, so the design choices stay with you and are not marked up.

Contractor works, including VAT Items we supply directly

Working total about 1,138,300 AED, before loose furniture and styling. Municipality permits and professional fees are handled separately.

Contractor works, by package

868,300 AED, WITH VAT
Joinery and fit-out369,18042.5%
Doors, windows, aluminium97,44011.2%
Air conditioning and extract87,67510.1%
Plumbing and electrical86,62510.0%
Structure and new room84,6309.7%
Tiling and porcelain77,3858.9%
Ceilings and paint65,3627.5%
Total868,297100%

The contractor half of the split above, levelled and including VAT, on Retouch Decor's figures. Joinery is over two fifths of the contract, and the commitment most affected by a change of mind once manufacture starts.

Inside the items we supply directly

Materials and fittings
222,000
Curtains, site and handover
48,000

Indicative allowances for planning, not quotations. Hover a bar for what it covers.

What we need from you

The first three sit on the critical path. The rest can follow once the contract is signed.

DecisionWhy it mattersWhen we need it
Budget approvalConfirms the working total and lets us close the awardBefore award
Permit for the additional roomNo contractor includes municipality approval. Building without it carries a fine and removal riskImmediately, it delays the build
Tile and parquet selectionWe supply the materials. Long lead items, and the wet trades cannot start without themWithin two weeks
Lighting layoutMust be frozen before ceilings close, or changes become chargeableBefore ceilings start
Sanitary ware and mixersSelections drive the position of first-fix pipeworkBefore first fix
Kitchen appliancesCut-out sizes are needed before the kitchen is manufacturedBefore joinery manufacture

Next steps

How we are protecting you

  • Air conditioning substantiated before it is ordered: heat load, equipment schedule and cost split. The package stays with the main contractor, so one company owns the ceilings, ductwork and electrical together.
  • A written completion date, a defects liability period, and a warranty on the air conditioning.
  • Every item a contractor says is included confirmed in writing, so nothing rests on a conversation.

Programme

  • Second meeting with Retouch Decor: 5 or 6 September.
  • Revised quotation from Victorian Art: expected shortly.
  • Air conditioning substantiation: in parallel.
  • Award and mobilisation once budget and permit are settled.
  • Construction: around six months, to be confirmed in a written programme.

The villa will not be habitable during the works.

Commercial terms side by side

TermRetouch Decor, revisedVictorian Art
Pricing basisLump sums, "as per drawing". Only doors and AC units now carry a countMeasured BOQ with sqm and lm rates on most lines
VATNot printed, but confirmed exclusive as usual. 5% adds 40,998, giving 860,9485% shown, 40,758
Advance70%, now about 574,000 across four quotes428,000, about 50%, non-refundable
Balance30% on completionFour further payments on the BOQ, not tied to milestones. The AC quote says simply "full payment"
DurationStill not statedSix months estimated
ApprovalsExplicitly excluded and placed on the client, in writing on Q1365 rev01Government clearance and passes by the owner
Validity"35 days from advance payment", wording still illogicalNot stated
VariationsAnything not listed is a variation; extra per sqm for changes after ceilings close20% fee on any cancelled item
Exclusions listedSpot lights, chandeliers, wall lights, WCs, mixers, kitchen appliances, door handles, porcelain and parquet materials. The printed list still says wallpaper, which the contractor has since confirmed is included; the document needs correctingPorcelain and parquet, kitchen marble, doors and aluminium, sanitary fixtures, electrical accessories
Location on documentDubai, Hatta on all four"UAE, Dubai", Hatta not written; client name blank
Warranty and snaggingNot mentioned, including for ACNot mentioned

Clarification lists

For Retouch Decor, round two

  1. Duplicate plumbing line. Withdrawn in rev01.
  2. Game or play room. Now priced at 24,500.
  3. Internal doors. Now priced, six at 2,650.
  4. Approvals. Now written as the client's responsibility.
  5. AC heat load and build-up. Provide the calculation behind 15 TR, the room-by-room split across the three units, thermostat count and zoning, and whether the new external room and external kitchen are served. With it, the equipment schedule with model numbers and a cost split between equipment, ductwork and labour.
  6. AC and ceiling coordination. Are duct bulkheads, grille openings and access panels inside the 62,250 ceiling price, or a variation? Confirm in writing.
  7. Electrical supply. Does the villa have three-phase, and is any DB or supply upgrade needed for three condensing units? Who pays?
  8. Old AC removal. Who strips out and disposes of the existing system?
  9. Internal door specification. "Halo cheep board" reads as hollow chipboard core. At 2,650 a leaf that is an entry-level door in a villa where the dressing room alone is 52,500. Price a solid-core or engineered-core alternative and confirm the count of six is right against the plan.
  10. Aluminium schedule. 45,800 covers "all" windows with no schedule. Provide the window count, sizes, system brand, glass build-up, thermal break profile, colour and whether mosquito screens are included.
  11. Aluminium overlap. Q1365 says remove all aluminium windows and doors and install new windows. Q1364 prices four external aluminium doors separately. Confirm there is no double-count and that every removed door is replaced.
  12. Drainage. The plumbing line says water pipes only. Is drainage, floor drains and chasing inside the 32,000, and is bathroom wall waterproofing included or only floors?
  13. VAT on the document. Confirmed exclusive verbally. Have the reissued quotes print the net, the 5% and the gross, with the TRN, so the contract matches the invoices.
  14. Master wardrobe island, in writing. Confirmed inside the 52,500 dressing room. Add it to the description.
  15. Quantities. Reissue with measured quantities and rates. Our benchmark areas are roughly 245 sqm of ceiling, 22.5 sqm of living room cladding and 39 lm of master wardrobes; we will check the reissue against those.
  16. Programme. Total duration, completion date, and the sequence across the four packages including where AC sits before ceiling closure.
  17. Hatta logistics. Mobilisation, accommodation, transport, and how often the engineer is on site.
  18. Kids bedroom, in writing. Confirmed the study desk and wardrobes are inside the 39,500. Have the line description say so, and confirm what the 24,500 play room covers separately so the two rooms do not overlap or leave a gap.
  19. Wallpaper, in writing. Confirmed included verbally, but Q1364 rev02 still lists "wall paper" under Exclude. Delete it from the exclusion list in the reissued quote and state the rooms and areas covered.
  20. Disposal. Skips, transport and municipality waste fees inside the 15,600?
  21. Warranty. Defects period on joinery, waterproofing, aluminium and AC, plus compressor warranty and a first-year AMC price.
  22. Validity. Correct the wording to run from the quote date.

For Victorian Art

  1. Duplicate demolition line. Items 11 and 12 are identical. Is 42,000 double-counting?
  2. Tiling. Price the fixing labour, or accept that another contractor tiles over their waterproofing and say how they will coordinate it.
  3. Kitchen worktop. Price porcelain or quartz with splashback.
  4. Wall paint. Item 41 is ceilings only. Price walls.
  5. Bathrooms. Price three vanities, mirrors and shower partitions, and confirm whether the powder room was in the drawings they priced.
  6. Wardrobe measure. Justify 39 lm at 2,550 against the plan, with height and depth.
  7. Egger specification. Board thickness, decor codes, edge banding, hardware brand, LED driver brand.
  8. Payment. Map the five payments to milestones and reduce the advance.
  9. Cancellation. Remove or cap the 20% fee.
  10. Programme. A bar chart for the six months with material lead times.
  11. Clean BOQ. Several section totals are mislabelled. Reissue before it becomes a contract document.
  12. Warranty. Defects period and Hatta supervision arrangement.

Cautions

Retouch Decor

70% advance on a bigger numberhigh, now worseThe advance is now about 574,000 AED net, 603,000 with VAT, up from 474,000, still against lump sums with no quantities, no programme and no completion date. This is the single item to fix before anything is signed. It has grown precisely because the offer improved.
AC priced at a third of the competing quotehigh, reframed76,500 for 15 TR looked competitive on its own. Beside Victorian Art's corrected 150,000 for 13 TR it still looks like a different scope wearing the same words. No load calculation, no bathroom extract, no zoning statement, no allocation for the new room. A price this far below the only other bid is a warning, not a win. No calculation and no equipment schedule, no order.
Ceiling price predates the AC scopehighThe 62,250 ceiling quote is unchanged from before AC existed, and the terms charge extra for any modification after ceilings close. Ductwork, bulkheads, grille openings and access panels must be confirmed inside the ceiling price now, in writing, or this becomes the most predictable variation on the job.
Three inclusions exist only in conversationhighWallpaper, the kids desk and wardrobes, and the master wardrobe island are confirmed included, and together they are worth roughly 45,000. None appears in the documents, and Q1364 rev02 still lists wallpaper under Exclude. As it stands, the signed paperwork says the opposite of the agreement. Fix this in the reissued quotes before award, not after.
Internal door specification is below the room it opens intomediumA hollow chipboard core leaf at 2,650 sits in a villa with a 63,500 kitchen and a 52,500 dressing room. Either upgrade the door or accept the mismatch knowingly. Handles are excluded too.
Aluminium is a 45,800 lump with no schedulemedium"All windows as per site requirement" with no count, no sizes, no system and no glass spec. This is the easiest line on the whole offer to argue about later.
Possible aluminium overlapmediumQ1365 removes all windows and doors; Q1364 separately prices four external aluminium doors. Confirm the boundary.
Drainage still unnamedmediumRemoving the duplicate plumbing line was right, but the surviving 32,000 line only mentions water pipes. Do not assume drainage is inside it.
Approvals moved to TohfamediumClear, but it is now an unpriced Tohfa line. Budget the permit, the structural drawings and the consultant, and settle who submits before the new room starts.
Still no programme, quantities or warrantymediumFour revisions and none of these appeared. They respond to scope requests readily and to commercial requests not at all. Read that as a negotiating signal.

Victorian Art

A 100,000 error in the AC quote, corrected verballyhighThe issued quotation prints 250,000. Victorian Art now say it should read 150,000, a 40% movement on a single line, described as a typing error. Blank quantity and rate columns are why nobody could catch it. Take nothing on this package as settled until a corrected quotation is issued in writing, and treat it as a warning about the checking behind the rest of the BOQ, which already carries a duplicated demolition line and mislabelled section totals.
"Full payment" on the AC packagehighThe AC quote's payment term is two words, with the non-refundable advance and 20% cancellation clauses still attached. Read literally it means paying the whole amount before a unit is installed. Do not treat this as a typographical slip; ask them what it means and get it replaced with milestones.
The offer is still materially incompletehighAC is now covered, but roughly 252,000 AED of work remains excluded: all aluminium, all doors, tiling, wall paint, worktop, bathroom joinery and external paint. Their BOQ still reads complete, which is the risk.
20% cancellation fee plus non-refundable advancehighUnchanged and unacceptable while drawings are still moving.
Partial response to round onemediumRetouch Decor turned a meeting into four revised documents. Victorian Art produced one new quote for the single package with the largest margin in it, and left the seven items that would have cost them money untouched. That is a choice, not an oversight.
Document quality and project identitymediumBlank client, "Dubai" not Hatta, duplicate demolition line, mislabelled section totals.

Both

The cover totals still do not compareThey now read 860,948 against 1,013,408 on the corrected AC figure, and that gap understates the position, because Victorian Art's total excludes aluminium, doors, tiling, wall paint, worktop, bathroom joinery and external paint. Only the levelled view, 868,300 against 1,278,600, compares like with like.
Municipality approval for the new roomNow formally nobody's but Tohfa's. Building without it in Hatta carries fine and demolition risk.

Recommendation

Award to Retouch Decor, subject to four commercial conditions. Give Victorian Art one final deadline, then close them out.

Retouch Decor now offers a near-turnkey villa at roughly 868,300 levelled against Victorian Art's 1,278,600, and they demonstrated something no document can show: they took a meeting, went away, removed a line that was in their own favour, and came back with three new packages in days. The one part of their offer this evaluation cannot yet endorse is the air conditioning, which Victorian Art's quote has now called into question from the opposite direction.

What has not improved is the commercial paperwork. Four revisions produced no VAT position, no quantities, no programme and no warranty. That is now the entire remaining negotiation.

Conditions before award

  1. Payment restructure. Milestone payments in place of 70% up front: 25 to 30% on mobilisation, then first fix complete, ceilings closed, joinery delivered, handover, with 5 to 10% retained for 90 days. This is the one condition worth losing the contractor over.
  2. AC substantiated before it is ordered, and kept with the main contractor. No order on Q1366 until five things arrive: the heat load calculation room by room, the equipment schedule with model numbers, a cost split between equipment, ductwork and labour, the zoning and thermostat allocation including bathroom extract and the additional room, and written confirmation that duct bulkheads and grille openings sit inside the ceiling price. Splitting this package to a separate supplier is not the answer in Hatta; substantiating it is.
  3. Quantities and schedules. Reissue the four quotes with measured quantities, plus a window schedule for the 45,800 and a door schedule for the 15,900. Benchmark against the VA BOQ where it helps.
  4. Programme and warranty. A completion date, and a defects period covering joinery, waterproofing, aluminium and AC. VAT is settled as exclusive; have it printed with the TRN on the reissued quotes.

How to run the negotiation

Do not open by asking for a discount. The price is already well positioned and pushing on it invites specification erosion in exactly the places that are already thin, the internal doors and the AC. The scope questions are now closed, so spend the leverage on payment terms and on upgrading the internal door cores at the same price, which costs them perhaps 10,000 and costs Tohfa nothing in quality.

Victorian Art

Their AC quote has been useful in one specific way: it proved that Retouch Decor's AC price needs checking. Beyond that, they answered one package out of eight and priced it at a level that is hard to explain. Send the unified scope list with a firm date. If they come back complete, competitive and with Hatta confirmed, reopen. Otherwise thank them and close.

Single contract, deliberately

The villa goes to one contractor, air conditioning included. Hatta is far enough that every extra trade means another mobilisation, another supervision visit and another party to chase for a snag. A split award doubles the interface risk exactly where it hurts, in the bathrooms and kitchen where wet trades, ceilings, ductwork and joinery all meet, and it is Tohfa that absorbs the coordination in time. The AC price gets substantiated inside the contract instead: heat load, equipment schedule, cost split.

Tohfa's own lines to budget now

Municipality approval and structural drawings for the new room, sanitary ware and mixers, light fittings and switches, tile and parquet materials, kitchen appliances, door handles, curtains and styling. Keep these under Tohfa's own procurement rather than letting either contractor mark them up.

Negotiation views

Price and scope review

Internal, full picture

GroupRetouch DecorVictorian ArtDifferenceVarianceNote
Enabling and structural80,60090,000+9,400VA +11.7%Nets out. VA demolition is 169% higher, RD's new room is 35% higher
MEP first fix82,50080,500−2,000VA −2.4%The only group where the two effectively agree
Air conditioning76,500150,000+73,500VA +96.1%Corrected verbally from 250,000. Neither figure verified; benchmark before ordering either
Doors, windows and aluminium92,800not offeredn/an/aVA excludes the whole group
Ceilings, paint and finishes62,250102,550+40,300VA +64.7%VA is genuinely more specified: MR and HR boards, bulkheads, openings. But no wall paint
Tiling and porcelain labour73,700not offeredn/an/aVA excludes the whole group
Joinery and fit-out351,600542,100+190,500VA +54.2%The largest group in the project. VA is higher in every room except the entrance
Total before VAT819,950965,150+145,200VA +17.7%VA's total also excludes two entire groups

Joinery and air conditioning account for 264,000 of the 145,200 headline difference, offset by the two groups Victorian Art does not price at all.

What sits behind the joinery group

RoomRetouch DecorVictorian ArtVariance
Entrance21,50019,720RD +9.0%
Majlis and dining51,60059,200VA +14.7%
Living room29,00058,250VA +100.9%
Kitchen63,500111,800VA +76.1%
Master bedroom84,700158,520VA +87.2%
Kids bedroom39,50082,740VA +109.5%
Play or game room24,50051,870VA +111.7%
Bathroom joinery37,300not quotedn/a
Joinery total351,600542,100VA +54.2%

Read the room differences with care. Victorian Art's kids bedroom and play room include wardrobes, a study desk, a library unit and a bunk bed with slide that Retouch Decor's lines describe more briefly. Some of the gap is content, not margin. The kitchen gap runs the other way: Victorian Art is 76% higher and still excludes the worktop.

Price groups, Victorian Art

Price comparison by work group

Groups where the offer sits above our benchmark

GroupQuotedAbove benchmarkDifferenceWhat we want from the conversation
Air conditioning150,000+96.1%+73,500Reissue the quotation with the corrected figure, then a breakdown by equipment, ductwork and labour, and the heat load behind 13 TR. The package cannot proceed on a verbal correction
Play or game room51,870+111.7%+27,370Confirm the wardrobe run against the plan. Price the room without the wardrobes as an option
Kids bedroom82,740+109.5%+43,240The bunk bed at 33,000 and the desk at 14,430 drive this. Show us the design that justifies them
Living room58,250+100.9%+29,250The TV unit at 24,200 is the outlier. What changes if it is simplified?
Master bedroom158,520+87.2%+73,82039 lm of wardrobes at 2,550. Walk us through the measure on the plan, with height and depth
Kitchen111,800+76.1%+48,30076% above benchmark and the worktop is still excluded. Include it and revisit the cabinet rate
Ceilings, paint and finishes102,550+64.7%+40,300We accept MR and HR boards add cost. Wall paint is missing entirely, which has to be added
Demolition42,000+169.2%+26,400Items 11 and 12 are identical. Confirm this is not double counted
Majlis and dining59,200+14.7%+7,600Broadly acceptable. Confirm the line order, the printed sequence does not read cleanly

Scope in our requirement that your offer does not cover

ItemWhat we need pricedStatus in your offerPriced by the other party
Aluminium windows, whole villaRemove the existing units and install thermal break, double glazed windows throughout, including the additional roomExcludedQ1365 rev01, 45,800
External aluminium doorsFour single leaf, thermal break system with double glassExcludedQ1364 rev02, 4 x 2,250
Main entrance doorAluminium frame with double tinted glass, solid core leaf, hinges and closerExcludedQ1364 rev02, 15,600
Internal doorsSix leaves with solid frame and architrave, to a core specification we will agreeExcludedQ1364 rev02, 6 x 2,650
Existing villa doorRe-dress to match the new conceptNo lineQ1364 rev02, 6,500
Floor tiling and parquet, fixing labourAll areas including skirting. Materials supplied by usExcludedQ1365 rev01, 42,500
Wall porcelain, fixing labourBathrooms and kitchen. Materials supplied by usExcludedQ1365 rev01, 31,200
Kitchen worktop and splashbackPorcelain or quartz, matched to the cabinets you have already quoted. Without it the kitchen cannot be handed overExcludedQ1364 rev02, inside 63,500
Internal wall paintAll walls not clad or papered. Your item 41 covers ceilings only, so no wall in the villa is currently paintedNo lineQ1363 rev01, 24,500
External paintThe new area, matched to the existing villa finishNo lineQ1363 rev01, 6,250
Powder roomThe room does not appear anywhere in the BOQ. Confirm whether it was in the drawings you pricedNo lineQ1364 rev02, 10,500
Bathroom joinery, three roomsCounters with porcelain tops and built-in sinks, drawers and shelves, wall mirrors, a wall cabinet to the master, and glass shower partitionsNo lineQ1364 rev02, 37,300

Additional scope we need priced

ItemWhat we need pricedStatus
AC to the additional room and external kitchenYour zoning covers living, dining and majlis, master and dressing, and kids, game room and hallway. Neither external space is served, and the new room has a sandwich panel roofPrice

Not a price question, but on the agenda

  • Seven packages are still excluded: aluminium, all doors, tiling labour, wall paint, kitchen worktop, bathroom joinery and external paint. We need a yes or no on each.
  • The powder room does not appear anywhere in the BOQ.
  • "Full payment" on the AC quote has to become milestones.
  • The 20% cancellation fee and the non-refundable advance are conditions of award, not details.
  • The clause charging for "any accessory not specified by the client" is open-ended. Define it or delete it.
  • Several section totals are mislabelled. Reissue clean before it becomes a contract document.

Price groups, Retouch Decor

Price comparison by work group

Groups where the offer sits above our benchmark

GroupQuotedAbove benchmarkDifferenceWhat we want from the conversation
Additional room structure65,000+35.4%+17,000Break it into blockwork, roof and slab so we can see the build-up. The roof specification drives the number
Electrical first fix35,000+32.1%+8,500Give us the point count by type. At this level we expect a schedule, not a lump sum
Entrance joinery21,500+9.0%+1,780Marginal. Confirm the mirror and cabinet extent and we will leave it

Three groups, 27,280 in total. The rest of the offer is at or below benchmark, so this is a short price conversation by design. Do not push harder than this: pressure on a well-priced offer buys specification erosion, not savings.

Scope in our requirement that your quotes do not name

ItemWhat we needAskPriced by the other party
Bathroom exhaust fansExtract fans with ducting and grilles to all bathrooms. Nothing in the AC quote covers extractPriceRef 1108, in 250,000
Bathroom wall waterproofingYour line covers floor insulation. Shower walls need tanking to full heightConfirm or priceRef 1103, in 54,000
Drainage pipeworkYour line names water pipes. Drainage, floor drains, sanitary points and chasing must all be inside itConfirmRef 1103, in 54,000
Concealed cistern enclosureCement board enclosure wherever cisterns are concealed within the wallConfirm or priceRef 1103, item 35
Moisture and heat resistant ceiling boardMoisture resistant board to bathroom ceilings and heat resistant board to the kitchen ceiling, not standard board throughoutConfirmRef 1103, items 37 to 38, 15,750
Bulkhead ceilingsBulkheads where the design requires them and wherever your own AC ductwork needs to be concealedConfirmRef 1103, item 39, 11,250
Ceiling openings for track and LED lightingOpenings with support boards, roughly 80 positions across the villaConfirmRef 1103, item 40, 80 at 75
Wardrobes to the play roomYour line covers cladding, a desk and a bench. The design also shows wardrobe runs in that roomPriceRef 1103, game room, 11.5 lm
Rounded corner claddingCorner cladding at the entrance, majlis and living roomConfirmRef 1103, items 45, 47, 56
Cabinet doors to the electrical boxesConcealment doors to the distribution boards, finished to match the surrounding claddingConfirm or priceRef 1103, item 44, 13 at 340
Demolition disposalSkips, haulage and municipality waste feesConfirmRef 1103, items 9 to 12
AC zoning and thermostatsRoom by room allocation across the three units, and the thermostat count. Bedrooms sharing a thermostat with living space will not be acceptedConfirmRef 1108, items 1 to 2
LED-lit wall claddingCladding with integrated LED lighting at the entrance and majlis. Your lines describe laminated cladding with porcelain and do not mention lightingConfirm or priceRef 1103, items 46, 49
Backlit mirrorEntrance mirror with backlit LED. Your line specifies clear mirror onlyConfirm or priceRef 1103, item 51

Additional scope we need priced

ItemWhat we need pricedStatus

Points to verify

GroupQuotedWhy we are asking
Air conditioning76,500Well below what we expect for three zones with full ductwork. We need the heat load, the room-by-room unit allocation, the thermostat count, bathroom extract, and cover for the additional room. We are not asking you to reduce this, we are asking you to prove it is complete
Ceilings and ductwork31,500Priced before the AC package existed. Confirm in writing that duct bulkheads, grille openings and access panels are inside it
Plumbing32,000The line says water pipes. Confirm drainage and bathroom wall waterproofing are included
Internal doors15,900A hollow chipboard core leaf sits below the rest of the specification. What does a solid core cost, and is six the right count?
Aluminium45,800A lump sum for "all windows". We need a schedule with counts, sizes, system, glass build-up and colour

Documentation and commercial

  • Three items are included by conversation only: wallpaper, the kids study desk and wardrobes, and the master wardrobe island. The exclusion list still contradicts one of them. Put all three into the reissued quotes.
  • Reissue with measured quantities and rates, not lump sums.
  • 70% advance becomes milestone payments with retention.
  • A completion date and a programme across the four packages.
  • Defects liability period, plus compressor warranty on the AC.
  • VAT printed with the TRN on the face of each quote.
  • Fill in the blank "facilities to be provided by client" list.
  • Correct the validity wording to run from the quote date.

Meeting preparation

Retouch Decor, second meeting

What you must leave with

  • Agreement in principle on milestone payments and retention
  • The AC heat load and zoning split, and the ceiling and ductwork confirmation in writing
  • Window and door schedules behind the two lump sums
  • A completion date, and VAT printed with the TRN on the reissued quotes

Agenda

  1. Acknowledge the revisions and confirm the four totals: 282,600, 398,600, 62,250, 76,500 (5 min)
  2. AC: load, zoning, thermostats, new room, three-phase supply, old system removal, ceiling coordination (20 min)
  3. Aluminium and doors: schedules, specification, the Q1365 and Q1364 overlap, the door core upgrade (15 min)
  4. Open items: drainage, disposal, and getting the three verbal inclusions written into the quotes (10 min)
  5. Commercial: payment structure, programme, warranty, validity (20 min)

Questions to press on

  • "Show me the heat load. Which rooms sit on each of the three units?"
  • "Is the ductwork bulkhead inside the 62,250, yes or no, in writing?"
  • "How many windows does the 45,800 cover, and at what glass build-up?"
  • "Q1365 removes all doors. Q1364 replaces four. What happens to the rest?"
  • "A hollow-core door into a 52,500 dressing room. What would solid core cost?"
  • "Does the 32,000 include drainage, or only supply?"
  • "Where are the bathroom exhaust fans, and which unit serves the new room?"
  • "Your exclusion list still says wallpaper. Delete it and describe what is covered."
  • "When do you finish, and what do you want on each milestone?"

Levers

  • Four packages awarded together, a full turnkey contract for one contractor
  • Tohfa handles approvals and supplies materials, which frees their working capital
  • A completed Hatta villa reference and repeat work across Tohfa's pipeline
  • Their own revision has already shown the flexibility; ask them to finish the job on terms

Red lines

  • No advance above 30% without security
  • No AC order without the load calculation, the equipment schedule and the cost split
  • No signature while the ceiling and ductwork boundary is verbal
  • No contract without a completion date and a defects period

Victorian Art, decision meeting

What you must leave with

  • A reissued AC quotation at the corrected figure, with a heat load and a rate breakdown behind it
  • "Full payment" replaced with milestones
  • A yes or no on aluminium, doors, tiling, paint, worktop and bathroom joinery
  • Hatta confirmed, client name corrected, a clean reissued BOQ
  • Removal of the 20% cancellation fee and a milestone payment map
  • A date by which the revised offer arrives

Agenda

  1. Where the tender stands: scope has grown, their offer has not moved (5 min)
  2. The unified scope list, package by package, in or out (25 min)
  3. BOQ corrections: the two page-2 lump sums, the duplicate demolition line, the 39 lm wardrobe measure (15 min)
  4. Commercial: advance, cancellation fee, programme, warranty (15 min)

Questions to press on

  • "The quotation says 250,000 and you now say 150,000. Send the corrected document, then break it down by equipment, ductwork and labour."
  • "What does full payment mean on this package?"
  • "Will you take aluminium, doors and tiling, or not? A clear no is useful to me."
  • "How do you propose to warrant waterproofing that someone else tiles over?"
  • "Walk me through 39 metres of wardrobe on the plan."
  • "Which lump sum is bathrooms and which is electrical?"
  • "Is the 20% cancellation fee negotiable? It is a condition of award."

Levers

  • Roughly 252,000 of additional work still available if they price it
  • Their own unit rates make it easy to show where a line is high
  • Tohfa as a repeat specifier across future villas

Red lines

  • No award with tiling sitting outside their waterproofing
  • No non-refundable advance without milestone protection
  • No 20% fee on items not yet started
  • No further extensions after this deadline

Unified scope list, updated

PackageRetouch DecorVictorian Art
Demolition and disposalQuotedDisposal?QuotedDuplicate line
Additional roomQuotedPartly
Aluminium windows and doorsQuotedNo scheduleExcluded
Plumbing and waterproofingQuotedDrainage?Quoted
Electrical first fixQuotedQuoted
Air conditioningQuotedLoad?Quoted3.3x the price
Ceilings and paintQuotedBulkheads?QuotedNo wall paint
Tiling and parquet labourQuotedExcluded
Internal and external doorsQuotedSpecExcluded
Bathroom joineryQuotedNot quoted
Kitchen with worktopQuotedCabinetsNo worktop
Bedrooms and play room joineryQuotedDescribe in the lineQuoted
Reception spaces joineryQuotedQuoted
WallpaperIncludedFix the exclusion listQuoted
Commercial: milestones, retention, warranty, programmeAll openPartly

Meeting notes

Tohfa Design LLC · Internal procurement document, round two, not for client distribution. All four Retouch Decor totals were recalculated line by line and reconcile to the printed figures. Victorian Art line-level pairings in the entrance and majlis sections remain a best reading of a scrambled layout.
Tohfa Design LLC · Prepared for discussion. Figures are transcribed from the quotations received and are subject to written confirmation.